June 6: Weekly Status Update

Please note that all published dates and timelines are subject to change. We appreciate your flexibility as we continue to refresh our campus!

Front Entrance & Grand Foyer: Began May 19
Preparation work continues. A construction zone perimeter fence wraps around the Fountain Plaza space and across the west entrances into the Grand Foyer. Recommended Sunday entrances into the church are: all east Grand Foyer doors and the north and south Atrium doors. A single west Grand Foyer door also remains accessible. Temporary handicapped parking has been designated in the unit of parking spots directly south of the Atrium. (See the below map for details.)

Click here to download the map as a PDF
 

Inside the Grand Foyer, temporary walls continue to be constructed along the front and west sides of the Grand Foyer. These walls will protect the interior of the church building from the outdoor elements as exterior work is done over the next several months.

The refresh to the front of the church and Grand Foyer includes a newly designed main entrance, community space in place of the fountain, streamlined entrances into the east and west Grand Foyer—including a covered drop-off of the west side—and some finishing updates and intentional spaces for community inside.

This phase of the project is expected to be completed in time for the holidays. Upon completion, construction will immediately shift to the east side of the Grand Foyer. For more details about this projects, click here.

Second Floor Classrooms: Began June 2
Another major project to reconfigure upstairs classrooms for our adult and student ministries is in its beginning phases. When work is completed, the student ministries (Middle & High School) will occupy the combined space that is now Rooms 215 and 216. Adult ministry spaces, meanwhile, will be consolidated into a suite of adjacent classrooms: combining Rooms 212 and 203, and combining Rooms 204 and 205.

While the schedule is fluid, this is the anticipated start schedule:

  • June 2: demolition works begins for Rooms 203 and 212.
  • June 9: demolition work begins for Rooms 204 and 205.
  • June 16: demolition work begins for Rooms 215 and 216.

These classroom remodels are anticipated to be completed for the fall semester, though, as always, timelines are subject to change as each project progresses.

Thank you for your continued flexibility! This construction work will certainly cause frustrations and inconveniences, but we are excited about the how God will use the work we’re doing now to impact people for generations to come.

Please note that all published dates and timelines are subject to change. We appreciate your flexibility as we continue to refresh our campus!