August 2: Weekly Status Update

Please note that all published dates and timeless are subject to change. We appreciate your flexibility as we continue to refresh out campus!

East Sanctuary, Room 215, CCP Restrooms: Happening Now
Remodel work to three sets of restrooms is underway. Work on the restrooms in the east Sanctuary hall and upstairs by Room 215 began July 8. These remodels are expected to last approximately 45 days. The restrooms in the preschool hallway began July 29. While these restrooms are closed, Sunday morning preschoolers will still have access to the in-classroom “Jack and Jill” bathrooms. These restrooms are expected to be completed by the time Central Community Preschool begins its fall session.

Gravel Road Paving: Week of August 5
Work on the gravel road on the west side of the Chapel is expected to begin the week of August 5. In addition to paving the existing gravel road, it will be extended with two-way traffic to the Maple Street entrance. The road is expected to be completed by the start of the school year. However, during construction the entrances to the west side of the parking lot could be impacted for Sunday mornings.

Sanctuary Stage: Week of August 12
The extension of the Sanctuary stage is now expected to begin the week of August 12 and continue for several weeks. During this time, worship services will continue in the Sanctuary.

Atrium and Second Floor Remodel: Details Coming Soon
Start dates for the remodel work planned for the Atrium and second floor classrooms and offices are being finalized. They will be shared as soon as they are available.