Please note that all published dates and timelines are subject to change. We appreciate your flexibility as we continue to refresh our campus!
Front Entrance & Grand Foyer: Began May 19
The preparation work that began last week continues. A construction zone perimeter fence wraps around the Fountain Plaza space and across the west entrances into the Grand Foyer. Recommended Sunday entrances into the church are: all east Grand Foyer doors and the north and south Atrium doors. A single west Grand Foyer door also remains accessible. Temporary handicapped parking has been designated in the unit of parking spots directly south of the Atrium. (See the below map for details.)

Click here to download the map as a PDF
New this week: Inside the Grand Foyer, temporary walls are now being constructed along the front and west sides of the Grand Foyer. This will likely be a multi-week project, so please expect to see incomplete work this Sunday. These walls will protect the interior of the church building from the outdoor elements as exterior work is done over the next several months.
The refresh to the front of the church and Grand Foyer includes a newly designed main entrance, community space in place of the fountain, streamlined entrances into the east and west Grand Foyer—including a covered drop-off of the west side—and some finishing updates and intentional spaces for community inside.
This phase of the project is expected to be completed in time for the holidays. Upon completion, construction will immediately shift to the east side of the Grand Foyer. For more details about this projects, click here.
Upcoming
Another major project to reconfigure upstairs classrooms for our adult and student ministries is expected to begin within the next few weeks. Please stay tuned for further details.
Thank you for your continued flexibility! This construction work will certainly cause frustrations and inconveniences, but we are excited about the how God will use the work we’re doing now to impact people for generations to come.
Please note that all published dates and timelines are subject to change. We appreciate your flexibility as we continue to refresh our campus!